Roof frame and block work
In my last blog post about this project we were just preparing the re-bar for the columns and beams of the concrete structure. Since then, we have completed all of the concrete structural work and have nearly completed the roof structure. Block work is about 80% complete and we are preparing to move on the roof tiling and rendering.
Another home construction project begins
In January, we were approached by a client to design their new home. Having started the design and engineering in February we were complete by the end of March. The house has two bedrooms, three bathrooms, open plan kitchen, dining and living room, a large home theatre room, garage with automatic roller door, a laundry room and a covered terrace at the rear.
We began construction just before the break for the Songkran festival. Currently, we have poured all of the concrete footings and are tying all of the re-bar cages for the grade beams.