Trees transplanted...

Yesterday we brought our new trees over from the orchard in which they were originally situated. We also had to remove one huge branch of a mango tree, which was cutting across the eventual position of the extended height fence we shall be putting up. Normally, I hate the idea of cutting down trees, but it didn't seem so bad in this case as we planted two to compensate.

Half of a mango tree is cut down Half of a mango tree is cut down

The tree on the left is the Rambutan on the one on the right is Lychee The tree on the left is the Rambutan on the one on the right is Lychee

Breaking ground

Right on schedule, we have begun work on our next Thip Thani project.  The lucky Buddhist day for the first column to be placed in the ground is next Thursday, 27th May.  Between now and then, the foundations will be dug, and all of the re-bar for the column and footing structures will be cut and tied.

Breaking ground on a new project Breaking ground on a new project

An overdue project update...

Well, it has been nearly two weeks since my last update about "Baan Sanploen" our first project in Thip Thani. There has been a lot of progress on the build, but also a few setbacks largely as a result of the recent political problems in Thailand. Many of our building supplies come directly from Bangkok and some things we source from local building supplies stores, but they in turn are also generally supplied from Bangkok. The mass protest in Bangkok lasted for over two months, but we felt the effect most in the final week. Delivery of many materials was delayed as they were either unable to get out of Bangkok or, in some instances, the factories had actually been closed completely for safety reasons, where they were situated close to the demonstrators. The stock in local building supply stores dwindled for some critical components. One example is for the cladding for decorative roof 'wing'. It is attached to the frame using a air nail gun and 2cm long nail strips..... the problem? we could not source the nails for the nail gun, so the roof wing construction stopped for two days. The day after the big crackdown by the military in Bangkok I went to Udon Thani to source some light fittings and plumbing supplies. However, as I reached Udon there was ominous black smoke rising up from somewhere in the town centre. This turned out to be from the town hall which had been set on fire. Many of the shops closed as a safety precaution, including my electrical and plumbing supplier.

I don't want to dwell or comment on the politics of the recent situation here, suffice it to say that the majority here hope that a long term resolution will be found and agreed upon by all parties, to save any future unrest.

Politics and delays aside, there has been a lot of great progress made by our hard working staff.

ROOF WING
Work began (then stopped due to lack of nails, then resumed!) on attaching the wood effect cladding to the wing structure... granted, it does not look much like wood yet, but reserve judgement until it has a few coats of wood stain applied! The finished effect should resemble that of a varnished dark wood texture.

Roof wing cladding Roof wing cladding

DOOR FRAMES
All of the door frames have been installed in the house

RENDERING
With all of the door frames installed, the last of the interior and exterior rendering has been completed.

EXTERIOR DETAILING
We have begun to apply the preformed detailing to the exterior of the house, namely around the windows and doors, amongst other places.

Exterior detailing being applied Exterior detailing being applied

PLUMBING
The exterior plumbing for the bathrooms has been fitted. This will be concealed behind decorative columns, as we did with the drain pipes. The concrete foundations for these columns have already been cast.

Exterior bathroom plumbing installed Exterior bathroom plumbing installed

WIRING
All of the first stage wiring has been completed in preparation for the suspended ceiling to be fitted. Any one used to traditional wiring methods in Thailand should notice an immediate difference from the photograph. We are wiring to international standards using grounded heavy duty pvc coated cable. Also note that insulation tape has not been used as the sole method of connection for adjoining wires - another somewhat scary method that appears to be a standard practice in Thailand!

Frist stage wiring First stage wiring

TILES
On my last trip to Udon Thani, I may not have managed to get the electrical supplies I went for, but I was able to order most of the floor and wall tiles for the house, which were delivered a couple of days ago.

Taking delivery of wall and floor tiles Taking delivery of wall and floor tiles

DOOR FITTINGS
We also recently took delivery of all of the door handles and other fittings including the rails and runners for the numerous sliding doors we have in the house.  As with the wiring, you may notice that these fittings are of a somewhat higher quality than the standard that one finds in Thailand.  Certainly, I can say with confidence that you will not find another rental property in Nong Khai with this quality of fixtures and fittings.

Door handles and lock Door handles and lock

TREES
It will soon be time to turn our attention to the garden and landscaping. We had always intended to plant some trees in the garden but had not given much thought to their type, so far. However, our future tenants expressed an interest in fruit trees. We didn't want to just buy saplings as we wanted to achieve the look of a more established garden from the start, so to begin with we have bought a Rambutan tree and Lychee tree which are both 10 years old and yield a lot of fruit as you can see in the picture below. They will be transplanted in the next few days, during which time many of the branches will be cut back. Anyone who has grown anything before in Thailand will know that the branches will grow back in no time given the amazing rate of growth that we get here.

The first tree for the garden - a 10 year old rambutan. The first tree for the garden - a 10 year old rambutan.

The new design...

Having spent the last 10 days consulting with our client, the redesign of our second project in Thip Thani is now complete.  Our client had been watching the progress of our first Thip Thani project "Baan Sanploen" and liked the general layout, but also loved the general look and feel of my original design for the second Thip Thani plot that I posted pictures of a couple of weeks ago.   So the new design could be considered to be a hybrid of the two designs.

Yesterday morning I passed on all of the architectural plan drawing to structural engineer.  I should have drawings back by the end of the week and break ground on Saturday.  The target completion date is early September.

Ground floor plan

Second floor plan Second floor plan









Overtime...

Well now, all of the door frames are in.  Almost all of the walls have been rendered.  The roof wing frame structure is complete.  I anticipate that there will be a lot of progress over the next week, as we are working overtime to ensure that we finish on schedule.

Sunset on the site Sunset on the site

Back to the drawing board...

Well, I had everything ready for our new project. All of the calcs had been done and we were all ready to break ground on the site. However, I was approached by someone who was very interested in our plot of land and who would like us to build a house for them... Great! Except that the house that I had already designed and was going to build does not fit with their budget and specification. Nevertheless, although it will mean a delay in the building work starting, it is obviously better to have a buyer lined up from the start of the project and a contract in place. So, it is back to the drawing board... I now have to prepare some concept drawings to give an idea of the sort of property we will be able to build for them to meet their budget and required spec. Once we talk through all of the options and all parties are happy, we will draw up a contract and begin the detailed design work. It is a little bit harder for me to estimate how long it will take to finalise he design when a third party involved... Obviously you have to be sure that the design is exactly as the client wants it, so it normally takes a little longer to tweak the final design. I will post some 3D renderings as soon as I have a (new) final design.

The time that I have put into the initial design, that we were going to build, will not be wasted as we will build it on another plot of land at a later date.

3D Rendered drawings

I have now passed on the plans for our next project to our structural engineer in order for him to perform all of the necessary calculations and produce all of the material we will need to pass on to the planning department.  Below are a few 3D renderings showing how the exterior of the finished home will look.








Roof Wing structure and door frames...

I last posted just over a week ago.  Since then there has been a reasonable amount of progress, though the workers have had a few days off.  It is the start of the rocket festival season in Nong Khai, and the staff have enjoyed a few days supporting their local village rocket team!  If you have never heard of the Isaan Rocket festival, it is quite a sight to be seen.  You can find out more about the Rocket Festival on our Nong Khai Information site here - http://events.nongkhaiinformation.com/Rocket_Festivals/

Back to the build.... most of the steel framework for the roof wing has been fitted.  Now that it is in place, you can see how much of a shadow they cast and how they will give a lot of much needed shade to the second floor windows and also to the balconies.  This is exactly the effect that was intended with the wing structure.

Steel roof wing structure Steel roof wing structure

All of the door frames have been custom made and today work began on installing them into the house.

First door frames fitted First door frames fitted

It has been a while since I have posted any videos to the blog, however, I shall be taking a few more and uploading them shortly.

Finalised design

Having been busy with client projects over the past week or so, I had somewhat neglected our next project in Thip Thani.  However, after a couple of days of focus I have now finalised the design for our second project in Thip Thani, which we will be offering for sale once completed.  If you like the idea of moving into a brand new home, finished to western standards, feel free to <a href="http://contact.nongkhaidesign.com/">contact us</a> to discus this or our future construction projects.  If you prefer, we can also help you find land and then design a build home to you exact specification and budget.

Any way, with that bit of shameless marketing out of the way, back to the project....

The house will again be two storey in order to maximise the available garden area.  The area of the plot is 400 sq.m. and the house will have a footprint of 90 sq.m. (not including a detached covered parking area).  The total internal floor area will be about 170 sq.m.

On the ground floor will be a family room, lounge, dining room, kitchen, laundry room and bathroom.  Then on the second floor will be the 3 en-suite bedrooms.    Below are my initial plan drawings of the house.  I shall also be producing a 3d rendered view of the property which I shall post to the blog in the next few days.

Once I have completed all of the detailed architectural drawings, I shall pass these on to our structural engineer to perform all of the calculations necessary to ensure the structural integrity of the building.  He will then produce the structural drawings the structural calculation report which will be submitted to the local planning department.

You may think this would be a long process if you have any experience of building projects in other countries.  However, in Thailand, obtaining planning permission is a very simple procedure. For our last project, it only took 30 MINUTES to obtain planning permission.

I anticipate all of the structural engineering and planning to be completed by the end of next week (7th May).  We will then be able to begin to prepare for construction by digging the holes for the footings.  This should tie in nicely with work being completed on our first Thip Thani project and our workers will be able to move seamlessly from one project to the next.

Ground Floor Layout Plan Ground Floor Layout Plan

Second Floor Layout Plan Second Floor Layout Plan

More rendering plus 'wing' construction

It's been a few days since my last post, but this is not to say that there has been no activity on site.  Most of the exterior has now been rendered.  The down pipes have been fitted to the roof guttering and today the concrete supports have been prepared for the brick work that will box in the drain pipes.  Also over the last couple of days, work has started on producing the steel structure for the 'wing' which will be fitted to the roof.

Roof wing frame structure Roof wing frame structure