Painting, Tiling and Window Fitting

We have now completely tiled the floor of the house and covered the floor with a layer of cardboard to protect the tiles whilst we complete the rest of the interior work.  We are also in the process of installing all of the windows and fitting out the bathrooms.  The granite for the kitchen counter top is due to de delivered and fitted by Monday, which will then allow us to complete the tiling and fitting of the kitchen cabinets and appliances. We have applied an undercoat and are now awaiting top coats of paint.